ASSA KONE DROUGHT PREPPAREDNESS PROJECT
Committed
KSh 55.1M
Delivered
100%
Funds absorbed
100%
County
Tana River
About this investment 01 · Record
Drought Preparedness Project
Delivery 02 · Progress
100%
Funds absorption
100%
Results & achievements 03 · Delivery record
What this investment set out to deliver — and how far each measure has come. Overall, 100% of the planned results have been achieved.
Output 1 · Improved access to water for communities and their livestock through development of climate proofed 50,000cum Kone Water pan and auxiliary structures
100%Water pan volumecubic meter
0 / 0
Water pan volume (completion status)cumBaseline 0 CUBIC METRES
50,000 / 50,000
Whole project · 50,000/50,000
Output 2 · Rehabilitation of Kone Bores for community use
100%Boreholes repaired
135 / 110
2023/24 Q3 · 35/102023/24 Q4 · 100/100
Output 3 · Improved community structures during drought preparedness through strengthened DRR committees.
0%DRR committee training/completed capacity building
0 / 0
Partners & funding 04 · Parties
Implementing partners
NDMACounty Government
Beneficiaries
HouseholdsCattleGoatsPrimary SchoolDispensaryPastoralist households