KYUASINI BOREHOLE EXTENSION (RESILIENCE) Project
Committed
KSh 5.9M
Delivered
100%
Funds absorbed
100%
County
Makueni
About this investment 01 · Record
Kyuasini borehole extension (Resilience) Project
Delivery 02 · Progress
100%
Funds absorption
100%
Results & achievements 03 · Delivery record
What this investment set out to deliver — and how far each measure has come. Overall, 100% of the planned results have been achieved.
Output 1 · 100
100%Kms of lines doneKmsBaseline 0
5 / 5
2026/27 Q1 · 5/5
Output 2 · Elevated storage tanks and interconnections
100%No. of elevated tankstanksBaseline 0
3 / 3
2026/27 Q1 · 3/3
Output 3 · Water points
100%No of distribution lines
6 / 6
2024/25 Q1 · 3/32026/27 Q1 · 3/3
Output 4 · water kiosks
100%Kiosks constructedkiosksBaseline 0
3 / 3
2024/25 Q1 · 3/3
Output 5 · Distribution lines
0%5KmsBaseline 0
0 / 0
Partners & funding 04 · Parties
Funding partners
European UnionCEFANational Treasury (GoK)
Implementing partners
NDMACounty GovernmentMOAMinistry of Water & Sanitation
Beneficiaries
HouseholdsCattleGoatsPrimary SchoolSheep