Rigdam Integrated Water Infrastructure Rehabilitation and Pipeline Extension project
Committed
KSh 29.0M
Delivered
56%
Funds absorbed
11%
County
Garissa
About this investment 01 · Record
Geographic Coverage Sectors Specific Objectives Outputs Beneficiaries Garissa Water Improved water access Rehabilitated water system Households: 800 Indicator Target Achievement INVESTMENT REPORT Rigdam Integrated Water Infrastructure Rehabilitation and Pipeline Ext
Delivery 02 · Progress
56%
Funds absorption
11%
Results & achievements 03 · Delivery record
What this investment set out to deliver — and how far each measure has come. Overall, 56% of the planned results have been achieved.
Output 1 · Rehabilitated water system
56%Households
25 / 45
2026/27 Q1 · 25/45
Partners & funding 04 · Parties
Funding partners
USAID
Beneficiaries
HouseholdsDispensary