KITHAMBA NGII WATER PAN
About this investment 01 · Record
Delisting and expansion of Kithamba Ngii Water Pan
Delivery 02 · Progress
Results & achievements 03 · Delivery record
What this investment set out to deliver — and how far each measure has come. Overall, 67% of the planned results have been achieved.
Output 1 · Output 1: desilting of the water pan and auxiliary works
100%Output 2 · Output 2: construction of the water tower and treatment facility with water point
0%Output 3 · Output 3: fencing of the dam
0%Output 4 · Output 4: rehabilitation of WASH accessories
0%Output 5 · Output 5: rehabilition water point and animal troughs
0%Output 6 · Output 8: Project management committee formed and trained
0%Locations 04 · Survey
1 site(s) surveyed for this investment
Partners & funding 05 · Parties
Funding partners
Implementing partners
Beneficiaries
Keywords 06 · Index
What delivery has taught 07 · Lessons
Lessons learnt
The PIT gave datailed project implementation the dam management committee overseeing the daily management of the dam
Challenges
encroachment by cattle as their is no fence resulting to siltation
Recommendations
fencing of the dam